Stage 3 Fire Strategy - Spatial Coordination
Introduction
A Stage 3 fire strategy develops the concept into a spatially coordinated fire safety design.
RIBA Stage 3 is Spatial Coordination. Architectural and engineering information should be coordinated so that the detailed technical design can proceed without major redesign of the building.
This is commonly the stage at which clients, building control bodies and contractors expect a substantial fire strategy report. However, Stage 3 is still not the completion of every specialist technical design.
Purpose
The Stage 3 strategy should:
- Test and validate the Stage 2 concept
- Coordinate fire safety measures with architecture, structure and services
- Undertake the necessary Building Regulations review
- Record key design decisions, risks and deviations
- Define the performance requirements for Stage 4 technical design
- Identify all specialist design responsibilities and interfaces
- Provide a defensible basis for planning, procurement or statutory submissions where applicable
The strategy should be detailed enough that unresolved fire safety matters do not cause major changes to the spatial design during Stage 4.
Required Inputs
The Stage 3 strategy should use:
- Approved Stage 2 fire strategy
- Coordinated plans, sections and elevations
- Confirmed occupancy and use schedules
- Structural design information
- MEP strategies and plant layouts
- Façade build-ups and materials
- Vertical transportation strategy
- Inclusive design strategy
- Specialist smoke-control, sprinkler and alarm input
- Fire service and building control feedback where available
- Existing-building survey results
- Planning conditions and fire statement commitments
- Insurer and warranty requirements
- Procurement strategy and responsibility matrix
Spatial Coordination
Means of Escape
The Stage 3 strategy should normally confirm and coordinate:
- Design occupancy by floor, area or use
- Occupancy load factors where applicable
- Travel distances
- Number and distribution of exits
- Exit widths
- Stair widths and capacities
- Stair protection
- Lobbies and protected corridors
- Alternative escape
- Dead ends
- Inner rooms
- Escape from basements and roofs
- Final exits and external routes
- Escape route signage and lighting principles
- Security controls on escape routes
- Accessible escape arrangements
- Evacuation lifts and refuges
The calculations and drawings should use the same occupancy assumptions.
Compartmentation
The Stage 3 package should define:
- Compartment floors and walls
- Sub-compartment boundaries
- Protected shafts
- Firefighting shafts
- Protected corridors and stairs
- Separation of uses
- Ancillary and high-risk accommodation
- Fire-resistance periods
- Fire door requirements
- Cavity barrier principles
- Service penetration strategy
- Junctions with roofs and façades
- Interfaces with smoke control and suppression
Compartment lines should be shown consistently on coordinated drawings rather than described only in text.
Structural Fire Safety
The strategy should coordinate:
- Required fire-resistance periods
- Loadbearing elements
- Compartment-supporting structure
- Transfer structures
- Structural protection systems
- Atrium or large-space conditions
- Any structural fire engineering
- Effects of movement on firestopping and façades
- Robustness and disproportionate collapse considerations where relevant
External Fire Spread
The Stage 3 strategy should establish:
- Boundary distances and space-separation approach
- Unprotected area calculations where required
- External wall material requirements
- Insulation and sheathing requirements
- Cavity barriers
- Fire stopping at compartment lines
- Spandrels and slab-edge interfaces
- Balconies, canopies and attachments
- Roof covering and roof junction requirements
- Evidence required for non-standard façade systems
Active Systems Coordination
Fire Detection and Alarm
The Stage 3 strategy should identify:
- System objective
- BS 5839 category or categories
- Areas requiring automatic detection
- Detector-type constraints
- Fire detection zones
- Alarm zones
- Simultaneous, phased or staged alarm arrangement
- Voice alarm requirements
- Visual and tactile alarm requirements
- Alarm receiving centre transmission
- Control and indicating equipment locations
- Repeater or fire-control panel requirements
- Interfaces with smoke control, lifts, doors, HVAC, access control and suppression
- Cable performance assumptions where these affect the strategy
- Resilience and network architecture requirements where relevant
For categories such as L2, L5 or P2, the protected areas and objectives should be clearly defined rather than stated by category alone.
Smoke Control
The Stage 3 strategy should coordinate:
- Design objectives
- Design fire and calculation basis
- Smoke-control zones
- Shaft and duct routes
- Vent and fan locations
- Replacement-air paths
- Pressure differential zones
- Power supplies
- Environmental and standby conditions
- Detection and control principles
- Firefighter controls
- Monitoring and fault reporting
- Interfaces with doors, dampers, lifts and ventilation
- Maintenance access
Sprinklers and Suppression
The Stage 3 strategy should coordinate:
- Design standard
- Hazard classification
- Coverage boundaries
- Tank, pump and valve-set locations
- Incoming water requirements
- Fire-resisting separation
- Monitoring and alarm signals
- Interfaces with smoke control and evacuation
- Fire-service connections
- Maintenance and replacement access
- Any compensatory role within the fire strategy
Stage 3 Cause-and-Effect Matrix
A Stage 3 cause-and-effect matrix should usually be a coordinated functional matrix.
It should identify, as applicable:
Causes
- Manual call points
- Automatic detectors
- Sprinkler flow switches
- Sprinkler valve tamper switches
- Suppression system signals
- Smoke-control system inputs
- Firefighter switches
- Evacuation controls
- Plant fire signals
- Gas detection or process safety signals where relevant
- Alarm receiving centre return or fault signals
Effects
- Evacuation or alert signals
- Voice alarm messages
- Visual alarm devices
- Alarm receiving centre transmission
- Smoke-control operation
- Damper operation
- Door release or closure
- Access-control release
- Lift recall, grounding or evacuation lift mode
- HVAC shutdown or mode change
- Gas, fuel or process isolation
- Sprinkler and suppression indications
- Fire shutters and curtains
- Wayfinding or dynamic signage
- Fire-service indications and controls
Logic
The matrix should define:
- Immediate versus delayed action
- Coincidence or confirmation requirements
- Investigation periods
- Escalation between alarm stages
- Relationships between fire detection zones and alarm zones
- Manual escalation controls
- Timer cancellation
- Reset and latching principles
- Dependencies on occupancy mode or time of day
- Required feedback and monitoring
The Stage 3 matrix may use functional groups, zone references or system groups rather than final point addresses. It should nevertheless be detailed enough for every discipline to understand what it must design.
What Should Develop Alongside the Stage 3 Strategy?
| Document or activity | Stage 3 purpose |
|---|---|
| Coordinated architectural drawings | Show escape routes, compartments, doors, shafts and firefighting facilities. |
| Compartmentation plans | Provide a clear graphical record of fire-resisting boundaries and ratings. |
| Fire door schedule or strategy | Defines ratings, smoke control, self-closing, hold-open and access requirements. |
| Occupancy and escape calculations | Demonstrate the capacity and arrangement of exits and stairs. |
| Structural fire engineering report | Develops any non-prescriptive structural fire solution. |
| Façade fire report | Defines materials, cavity barriers, slab-edge details and evidence requirements. |
| Smoke-control design basis | Records design objectives, calculations, zones, controls and interfaces. |
| Sprinkler design criteria | Defines standard, hazard, coverage, water supply and monitoring. |
| Fire alarm design brief | Defines category, coverage, zoning, warning and interface performance. |
| Functional cause-and-effect matrix | Coordinates the required actions across all systems. |
| Emergency lighting strategy | Coordinates coverage, duration, central supplies and controls. |
| Inclusive evacuation strategy | Develops refuges, EVC, evacuation lifts and assisted escape procedures. |
| Firefighting facilities drawings | Coordinate shafts, lifts, mains, access and fire-service controls. |
| Building Regulations review | Tests the coordinated design against all relevant functional requirements. |
| Stage 4 responsibility matrix | Identifies who completes each specialist technical design. |
| Procurement information | Defines fire safety requirements that must be preserved through procurement. |
Stage 3 Is Not Automatically Stage 4
A detailed Stage 3 report can still be incomplete for construction.
Typical Stage 4 items that may remain outstanding include:
- Final product selections
- Final wall, floor and door specifications
- Penetration and junction details
- Firestopping systems
- Final façade details
- Final smoke-control calculations and equipment schedules
- Final sprinkler hydraulic design
- Final fire alarm device and circuit design
- Final power-supply and battery calculations
- Final cause-and-effect implementation matrix
- Interface wiring and monitoring details
- Installation and commissioning procedures
- As-built evidence requirements
A Stage 3 strategy should identify these outstanding items and assign responsibility for them.
Procurement and Employer's Requirements
Where Employer's Requirements or tender information are issued at Stage 3, additional Stage 4-level information may need to be drawn forward.
The fire strategy should make clear:
- Which requirements are prescriptive
- Which are performance-based
- Which specialist designs remain contractor-designed
- What standards and acceptance criteria apply
- What submissions are required before manufacture or installation
- Who reviews contractor proposals
- How alternative products or value engineering will be assessed
- How fire strategy changes will be controlled
A statement such as “specialist contractor to design” is not sufficient unless the required outcome, interfaces and review process are defined.
Stage 3 Deliverables
A typical Stage 3 fire safety package may include:
- Stage 3 coordinated fire strategy
- Fire strategy plans
- Compartmentation plans
- Occupancy and escape calculations
- Fire-resistance schedule
- Fire door strategy
- Firefighting access and facilities drawings
- Fire alarm design brief
- Functional cause-and-effect matrix
- Smoke-control design basis
- Sprinkler or suppression design criteria
- Façade and external-wall fire strategy
- Inclusive evacuation strategy
- Emergency lighting strategy
- Fire safety design risk and assumptions register
- Building Regulations review
- Stage 4 design responsibility matrix
- Specialist design submission schedule
- Record of consultation and key decisions
Stage 3 Completion Criteria
Stage 3 should not be considered complete until:
- The architectural and engineering design is spatially coordinated
- Means-of-escape calculations agree with the drawings
- The evacuation philosophy is confirmed
- Compartment lines and fire-resistance periods are coordinated
- Firefighting access and facilities are coordinated
- Active system objectives and spatial requirements are confirmed
- The functional cause-and-effect is coordinated across disciplines
- Façade and external-wall requirements are defined
- Relevant Building Regulations requirements have been reviewed
- Major deviations and fire-engineered solutions are justified
- Specialist Stage 4 responsibilities are allocated
- Remaining technical design actions are clear
- The client has approved the Stage 3 fire strategy basis
Common Failures
- Calling a generic narrative a coordinated strategy
- Inconsistent occupancy figures between the report and drawings
- Compartment lines missing from drawings
- Fire doors specified without a coordinated function or schedule
- Leaving service penetrations and cavity barriers entirely to site resolution
- Alarm category stated without protected areas or system objectives
- Cause-and-effect limited to vague statements such as “all associated systems to operate”
- Smoke-control systems shown without replacement air or control philosophy
- Suppression systems used as compensation without identifying the dependency
- Façade details deferred until after procurement
- Specialist contractor responsibilities not defined
- Issuing tender information that permits alternatives with no fire safety review process
Relationship to Stage 4
Stage 4 should turn the coordinated design into complete information for manufacture, installation, testing and construction.
The Stage 3 package should give the Stage 4 designers:
- Fixed fire safety objectives
- Coordinated geometry
- Defined performance requirements
- Agreed system interfaces
- A functional cause-and-effect matrix
- A clear responsibility matrix
- Acceptance and submission requirements
- A controlled list of residual actions
Continue to Stage 4 – Technical Design.
Important: A Stage 3 strategy should be detailed enough to coordinate the building and define the Stage 4 requirements. It should not be mistaken for complete construction information unless the technical design has genuinely been completed.